National Secretariat

The past executive tried very hard to start the secretariat building on our land at Kuje in Abuja, but circumstances beyond their control made it impossible. The drawings of the first phase of the project are ready. The construction workers are doing excavation work on the site.

We sincerely hope to clear the site of all shrubs and bushes, and remove from site vegetable top soil (A of AUD 1 of 19) excavate vegetable top soil average 150 mm deep (B of AUD 1 of 19) by August, 2005. As these operations are going on, we will be pursueing the approval of the drawing by the Kuje Municipal Office in Abuja. Our member, Yahaya in Abuja is performing this task on our behalf. Based on these plans we implore all State chapters to come to Calabar ready to launch the secreatriate to enable us start the project.